Drill down production item to calculate purchase items in BOM

Posted on by 176
Hello experts, 
 
We are struggling with how to calculate planning for our sub-assembly production items. How do we use the demand forecast to predict how many sub assemblies we want to produce for the week to have the system calculate how much we need to purchase for all of our buy items for the sub assembly?
 
Does the planning worksheet calculate and drill down from the production bom into the components that make up the finished product?
 
 
  • Suggested answer
    Ben Baxter Profile Picture
    Ben Baxter 4,156 Moderator on at
    Drill down production item to calculate purchase items in BOM
    To add one more point to your question, "How do we use the demand forecast to predict how many sub assemblies we want to produce for the week", you generally build your Demand Forecast for your Finished Goods.  The forecast demand for the Finished Goods will determine which Sub-Assemblies are going to have demand, which in turn determines which purchased components are going to have demand.  You don't need to Forecast each level in your BOM, the system will see the subsequent lower-level demand created by the Finished Good's Forecast.
     
    Once you establish your Finished Goods Forecast, you are making a decision on HOW (stock vs. lean, etc.) to handle the demand generated for the sub-assemblies and purchased components.
     
    Best Regards,
    Ben Baxter
    Accent Software Inc
  • Suggested answer
    YUN ZHU Profile Picture
    YUN ZHU 62,477 Moderator on at
    Drill down production item to calculate purchase items in BOM
  • Suggested answer
    Ben Baxter Profile Picture
    Ben Baxter 4,156 Moderator on at
    Drill down production item to calculate purchase items in BOM
    The Planning Worksheet will scan through every level of your Bill of Material.  It will suggest Prod. Orders for your Sub-Assemblies.  It will suggest Prod. Orders for your Sub-Sub-Assemblies.  It will suggest purchases for the materials at all levels based on all suggested Prod. Orders (finished or sub-components).
     
    Once you understand how strong the calculation is, you'll want to define how you want the results to be.  Do you want your sub-assemblies on their own Production Order or nested on the Parent Item's Prod. Order?
     
    Don't forget, all Items have their own Planning settings.  You don't have to use Fixed Reorder, Lot-for-Lot, or Order for ALL Items, you get to mix and match based on your rules for the Item.  Beyond that, you get to make those decisions based on each plant/warehouse (a.k.a. Location).
     
    I would strongly recommend you reach out to your partner for a review of the Planning capabilities within Business Central.  There are a lot of great features, but with flexibility can come different configurations to dial in the planning for your business needs.  There are a lot of great sessions available on YouTube as well.
     
    Hope this helps get you started!
     
    Best Regards,
    Ben Baxter
    Accent Software Inc

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Dynamics 365 Community Update – Sep 16th

Welcome to the next edition of the Community Platform Update. This is a weekly…

Announcing Our 2024 Season 2 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Dynamics 365 Community Newsletter - September 2024

Check out the latest community news

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 283,860 Moderator

#2
Ludwig Reinhard Profile Picture

Ludwig Reinhard Microsoft Employee

#3
Martin Dráb Profile Picture

Martin Dráb 225,155 Moderator

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans